NEW QUESTION # 14
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?

  • A. Team Plan
  • B. Work Package
  • C. Product Description
  • D. Stage Plan

Answer: B

Explanation:
Section: Volume A


NEW QUESTION # 15
Identify the missing words in the following sentence.
PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

  • A. the project board
  • B. the change authority
  • C. corporate, programme management or the customer
  • D. the project manager

Answer: A


NEW QUESTION # 16
What do acceptance criteria identify?

  • A. The project controls set up during the process Initiating a Project
  • B. The approach that will be used to prove whether the project's products have been completed
  • C. A measureable improvement resulting from a project outcome
  • D. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders

Answer: D


NEW QUESTION # 17
Which statement defines a risk?

  • A. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
  • B. A certain event occurring in the future that will have a negative impact on the project's objectives
  • C. An event that has already occurred that the Project Manager must deal with immediately
  • D. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives

Answer: D

Explanation:
Section: Volume B


NEW QUESTION # 18
Which should be funded by a change budget?

  • A. Initiation stage
  • B. Handover activities
  • C. Increase in agreed scope
  • D. Change Authority

Answer: C


NEW QUESTION # 19
What theme estimates the cost of delivering the project?

  • A. Plans
  • B. Progress
  • C. Change
  • D. Business Case

Answer: A

Explanation:
Section: Volume B


NEW QUESTION # 20
What is a purpose of the communication management approach?

  • A. To document how the project team should control its interaction with stakeholders
  • B. To document the target organizational state required for the project to meet its objectives
  • C. To document how to use financial incentives to motivate project team members
  • D. To document the responsibilities of project team members for testing whether products are acceptable to users

Answer: A


NEW QUESTION # 21
Which is an objective of the Closing a Project process?

  • A. Prepare the plan for the next stage
  • B. Produce a Benefits Review Plan to identify what benefits are expected
  • C. Check that all benefits are realized before closing a project
  • D. Assess any benefits that have already been realized

Answer: D


NEW QUESTION # 22
Which theme provides all management levels within the project management team with mechanisms for monitoring and control?

  • A. Progress
  • B. Organization
  • C. Change
  • D. Quality

Answer: A

Explanation:
Explanation
Reference https://www.whatisprince2.net/prince2-theme-progress.php


NEW QUESTION # 23
Which role is responsible for the quality of the specialist products delivered in the project?

  • A. Executive
  • B. Project assurance
  • C. Senior user
  • D. Senior supplier

Answer: D

Explanation:
Explanation
Reference http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx


NEW QUESTION # 24
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  • A. Those who will specify the desired outputs of the project
  • B. Those who will manage the project on a day-to-day basis
  • C. Those with a financial interest in the project
  • D. Those who will create the project's outputs

Answer: B

Explanation:
Section: Volume A


NEW QUESTION # 25
Which is a type of issue?

  • A. An off-specification
  • B. A scope tolerance
  • C. Aproject outcome
  • D. An expected dis-benefit

Answer: A


NEW QUESTION # 26
Which is an objective of the quality review technique?

  • A. To provide a common understanding of what products a project will create
  • B. To define the quality methods required within a project
  • C. To determine the quality responsibilities of a project team
  • D. To baseline a product

Answer: D


NEW QUESTION # 27
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.

  • A. Configuration Item Records
  • B. project management team and/or role descriptions
  • C. Project Brief
  • D. Business Case

Answer: B


NEW QUESTION # 28
Which product defines how the project board should approve the management products produced during the 'initiating a project' process?

  • A. Project plan
  • B. Initiation stage plan
  • C. Communication management approach
  • D. Quality management approach

Answer: A


NEW QUESTION # 29
Which is a purpose of the 'initiating a project' process?

  • A. To enable an organization to understand the work needed to deliver the project's products
  • B. To enable the project board to decide whether it is worthwhile to initiate a project
  • C. To produce a stage plan for each stage of a multi-stage project
  • D. To provide a fixed point at which acceptance for the project product is confirmed

Answer: B

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Initiating_a_Project#Objective


NEW QUESTION # 30
......